File #: 13-74    Version: 1 Name:
Type: Resolution Status: Passed
File created: 4/24/2013 In control: City Council
On agenda: 5/15/2013 Final action: 5/15/2013
Title: A RESOLUTION AUTHORIZING THE CITY MANAGER TO ENTER INTO A CONTRACT WITH RONYAK PAVING, INC. FOR THE HINES HILL ROAD RESURFACING PROJECT (PID 92671); AND DECLARING AN EMERGENCY. Executive Summary: This project consists of asphalt planning; full depth repairs; intermediate asphalt course; surface course; berm restoration and pavement striping along Hines Hill Road from the Corp. Line near Walters Road to Prospect Street.
Sponsors: William A. Currin
Indexes: Engineering, Streets / Sidewalks
Attachments: 1. Bid Tabulation_Hines Hill Road Resurfacing, 2. Resolution No. 13-74
Title
A RESOLUTION AUTHORIZING THE CITY MANAGER TO ENTER INTO A CONTRACT WITH RONYAK PAVING, INC. FOR THE HINES HILL ROAD RESURFACING PROJECT (PID 92671); AND DECLARING AN EMERGENCY.
Executive Summary:   This project consists of asphalt planning; full depth repairs; intermediate asphalt course; surface course; berm restoration and pavement striping along Hines Hill Road from the Corp. Line near Walters Road to Prospect Street.
Body
Legislative History
12-63-Approved the LPA Agreement
Purpose & Explanation
Bids were received on May 10, 2013 @ 9:00am.  Below is the Engineer's Estimate along with the respective bids.
Engineer's Estimate = $450,542.20
 
Ronyak Paving, Inc.      $348,128.20
Perrin Asphalt Company, Inc.      $356,856.06
Shelly & Sands, Inc.      $388,908.85
The Shelly Company      $389,441.73
Karvo Paving Company      $390,237.61
Chagrin Valley Paving, Inc.      $390,486.21
Barbicas Construction Company, Inc.      $394,700.88
Burton Scot Contractors, LLC      $451,192.19
 
The City Administration is requesting City Council approval to authorize the City Manager to award and enter into a contract with Ronyak Paving, Inc. of Burton, Ohio for the Hines Hill Road Resurfacing Project (PID 92671).  The Engineering Staff is requesting a 10% contingency for any unforeseen issues that may arise during construction for a total contract amount of $382,941.02.
 
Total Project Cost = $382,941.02 ($348,128.20-Base + $34,812.82-Cont.)
City Cost = $76,588.20 (20%)
ODOT Cost = $306,352.82 (80%)
Timing Considerations
Upon authorization to proceed by the City Council, the administration will award and enter into a contract with Ronyak Paving, Inc. for the above.
Fiscal Impact
      X        Currently Budgeted
        Supplemental Appropriation Required
        Appropriation Not Required.
 
Recommendation
Suggested Action
Staff recommends that City Council approve this resolution authorizing the City Manager to award and enter into a contract with Ronyak Paving, Inc. for the Hines Hill Road Resurfacing Project (PID 92671) and we are requesting an emergency clause be added to this legislation in order to maintain the public health, safety and welfare and in order to meet ODOT's construction deadline.
Submitted by,
Anthony J. Bales, City Manager