Legislation Details

File #: TMP-8894    Version: 1 Name:
Type: Resolution Status: Agenda Ready
File created: 9/10/2026 In control: City Council Workshop
On agenda: 10/27/2026 Final action:
Title: A RESOLUTION AUTHORIZING THE CITY MANAGER TO ENTER INTO A PROFESSIONAL SERVICES CONTRACT WITH GAI CONSULTANTS, INC. FOR THE RE-DESIGN OF THE BARLOW ROAD SIDEWALK PROJECT. Brief Description: This would authorize a contract with GAI Consultants, Inc. for the re-design of the Barlow Road sidewalk project between Nicholson Drive and Lincoln Blvd.
Sponsors: Jeffrey L. Anzevino
Indexes: Engineering
Attachments: 1. Exhibit - Barlow Rd Sidewalk, 2. Draft Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

A RESOLUTION AUTHORIZING THE CITY MANAGER TO ENTER INTO A PROFESSIONAL SERVICES CONTRACT WITH GAI CONSULTANTS, INC. FOR THE RE-DESIGN OF THE BARLOW ROAD SIDEWALK PROJECT.

Brief Description:   This would authorize a contract with GAI Consultants, Inc. for the re-design of the Barlow Road sidewalk project between Nicholson Drive and Lincoln Blvd.

Body

Legislative History

15-0010 - Barlow Road Improvement Design Option Discussion (1/27/2015)
15-68 - Enter into a Design Contract with GPD Group (5/19/2015)
16-0020 - Barlow Road Improvements Discussion (2/23/2016)
16-68 - Advertise, Bid and Award a Contract for Barlow Road Widening, Phase I (5/23/2016)
16-135 - Advertise, Bid and Award a Contract for Barlow Road Widening, Phase II (work at railroad crossing) (8/16/2016)
16-154 - Advertise, Bid and Award a Contract for Barlow/Terex Road, W. Intersection Improvements, Phase III (10/4/2016)
18-77 - Enter into Addendum with GPD for Additional Consulting Services for Veterans Trail; (6/5/2018)
19-64 - Enter into a mitigation agreement with the NCRCPD to mitigate wetland impacts for the Veterans Trail Phase IV - Barlow Road Sidewalk project (4/16/2019)
19-74 - Authorizes Bid and Award of Veterans Trail Phase IV (5/21/2019)

Purpose & Explanation

At the request of Council, staff has secured the scope and fee for the design of the Barlow Road sidewalk project between Nicholson Drive and Lincoln Blvd. This new sidewalk is anticipated to be a 5-foot-wide concrete sidewalk along the north side of Barlow Road.

Part of the design includes a redesign of the sidewalk section between Nicholson Drive and the Hike & Bike Trail, which was originally designed in 2019 as an 8-foot-wide asphalt trail along the north side of Barlow Road. Due to residents’ feedback, that project was put on hold and never constructed.

The redesign will include any needed survey, geotechnical analysis, environmental mapping and permitting, preparation of preliminary engineering plans, public meetings, Council presentations, exhibits, utility and outside agency coordination, detailed plan preparation, property acquisition  mapping and legal description preparation, project specifications, cost estimating, pre-bid services, construction assistance, and other miscellaneous services, with the intention to bid this project for construction as early as fall 2027.

The City will pay for any permit fees and property purchases under a separate purchase order, as needed.

Staff contacted four professional engineering consultants based upon previous sidewalk and trail design experience including GPD Group, Environmental Design Group, Euthenics Inc., and GAI Consultants.  Staff scored each proposal and is recommending GAI Consultants with a total fee of $309,698.    Each consultant's base fee plus if authorized items proposal costs are listed below:

GAI Consultants Inc.                                                               $309,698

GPD Group                                                                                    $336,983

Euthenics Inc.                                                                                    $369,529

Environmental Design Group                                          Did Not Submit

As with other consulting proposals, staff is requesting a 10% contingency to handle any unforeseen issues that may arise during the design and investigation work on this project. The total requested fee, including the 10% contingency, is $340,668 ($309,698 base fee + $30,970 10% contingency = $337,327).

Legal Authority for Proposed Legislation

Pursuant to Charter Section 6.04, Contracts & Purchasing:

                                            Competitively bid and advertised for three consecutive weeks

                       Joint or Cooperative Purchase Program

                     X                       Professional Services

                       Other [provide explanation]

Fiscal Impact

                                            Currently Budgeted

                       X                        Supplemental Appropriation Required (2025 Excess Carryover funds 430-6240-52556)

                                            Appropriation Not Required. 

Does this legislation require use of an emergency clause?

                       Yes

                     X                       No

 

Recommendation

Suggested Action

Staff recommends that Council approve this authorization for the City Manager to enter into a professional services contract with GAI Consultants, Inc. for the re-design of the Barlow Road Sidewalk Project.

Submitted by,

Thomas J. Sheridan, City Manager
Brian Griffith, Assistant City Engineer

Bradley S. Kosco, P.E., P.S., City Engineer
Jonathon Szalay, PE, Senior Engineer