Title: Discussion Regarding Barlow Road Path/Walk Improvements Executive Summary: Staff would like to update Council on the design of the Barlow Road Path/Walk Improvements.
Sponsors: David A. Basil
Attachments: 1. Barlow Road Exhibits

Title

Discussion Regarding Barlow Road Path/Walk Improvements

Executive Summary:  Staff would like to update Council on the design of the Barlow Road Path/Walk Improvements.

Body

Legislative History

15-68 - Enter into a design contract with GPD Group
15-0010 - Discussion regarding design options was held on January 27, 2015.
16-0020 - Discussion regarding Barlow Road Improvements and Barlow/Terex Road Intersection
16-68 - Permission to Advertise, Bid and Award the Barlow Road Widening Project, Phase I
16-117 - Acquisition of Land at 1170 Barlow Road
16-135 - Permission to Advertise, Bid and Award the Barlow Road Railroad Profile Grade Change, Phase II
16-154 - Permission to Advertise, Bid and Award the Barlow Road / Terex Road Intersection Improvements, Phase III

Purpose & Explanation

Below is the outline for discussion:

                     Existing conditions - roadside ditches, drives, 60’ R/W (30’ per side), 23’ pavement (11.5’ per side) leaving 18’ for path/walk and ditch, trees

                     Proposed Project:

o                     Metro Parks Hike & Bike Path to Terex Road, 10’ path connecting to hike and bike path at south west quadrant of Terex and Barlow Road

§                     Signalized Ped Crossing at Terex Road

§                     Asphalt Surface

o                     Terex Road to East side of old Flood Company Parcels, 7’ Path

§                     Crosses Reserve Lane, Williamsburg Circle, Nicholson Drive

§                     Portion of curb added along Hole #9

§                     Asphalt Surface

o                     East side of old Flood Company Parcels to SR 91, 5’ Path

§                     Crosses Holland Drive

§                     Concrete Surface

Additional Considerations:

                     Public Meeting

                     Right-of-way impacts 32 work agreements

                     Tree impacts 95+/-; proposed landscaping

                     Drive impacts 30+/-

                     Drainage/Swales

                     Bike use = “sharrows” and path

                     ODNR Grant

                     Connection to Veterans Trail Phase 3

                     Budget

                     Schedule

Timing Considerations

A public open house will be held in the coming months with construction anticipated for 2018.

Fiscal Impact

                                            Currently Budgeted

                       Supplemental Appropriation Required

                       Appropriation Not Required.

 

Recommendation

Suggested Action

Staff recommends Council discussion.

Submitted by,

Jane Howington, City Manager

Thomas J. Sheridan, PE, PS, Assistant City Manager-City Engineer

Christopher J. Papp, PE, Assistant City Engineer