File #: 23-69    Version: 1 Name:
Type: Resolution Status: Passed
File created: 4/27/2023 In control: City Council
On agenda: 5/16/2023 Final action: 5/16/2023
Title: A RESOLUTION AUTHORIZING THE CITY MANAGER TO ADVERTISE FOR BIDS AND TO ENTER INTO A CONTRACT FOR THE DARROW ROAD PARK CREEK CLEANING WITH THE LOWEST AND BEST BIDDER. Brief Description: This project involves the removal of sediment from the existing drainage ditch, in order to improve storm water flows that runs from Darrow Road into Darrow Road Park. .
Sponsors: Jeffrey L. Anzevino
Indexes: Engineering
Attachments: 1. Darrow Park Ditch Cleaning Exhibit, 2. Resolution No. 23-69

Title

A RESOLUTION AUTHORIZING THE CITY MANAGER TO ADVERTISE FOR BIDS AND TO ENTER INTO A CONTRACT FOR THE DARROW ROAD PARK CREEK CLEANING WITH THE LOWEST AND BEST BIDDER.

Brief Description:  This project involves the removal of sediment from the existing drainage ditch, in order to improve storm water flows that runs from Darrow Road into Darrow Road Park. .

Body

Legislative History

None.

Purpose & Explanation

The scope of this project involves the removal of approximately 12 inches to 18 inches of sediment from a portion of the existing ditch that flows from Darrow Road (SR 91) into Darrow Road Park.  Work includes the excavation and haul-off of sediment from the ditch and restoration of disturbed areas to improve storm water flows.

During construction of the SR 91 North Turn Lane Project in 2019, staff identified that sediment in the existing ditch at this location was partially prohibiting flows away from Darrow Road.  Because of the sediment, during significant rain events, the existing stream in Darrow Park can back up into the local storm water system, creating the opportunity for overland flooding at lower-lying properties along Darrow Road and Herrick Park Drive. 

It was also identified during the SR 91 North Turn Lane project that the sediment was trapping water against the roadway embankment along Darrow Road, creating saturated soil conditions under the roadway near the park.  The saturated road base conditions can lead to eventual degradation of the roadway. 

The project includes cleaning approximately 850 feet of the ditch from the roadway, downstream along private properties into Darrow Park to allow for better storm water flows away from SR 91.  Staff is requesting work agreements from affected private property owners to perform the work and permanent easements from property owners to aid in future maintenance of the ditch. 

Note that a future project, funded by an Ohio EPA 319 Grant will focus on a stream restoration project within Darrow Park.   The stream restoration project is scheduled for 2024 and is being managed by the Tinkers Creek Watershed Partners.

See attached exhibit for more information.

The estimated cost of the project, with 10% contingency is $150,000.

Legal Authority for Proposed Legislation

Pursuant to Charter Section 6.04:

                     X                       Competitively bid and advertised for three consecutive weeks

                       Joint or Cooperative Purchase Program

                       Professional Services

                                            Other

Fiscal Impact

                     X                       Currently Budgeted (504 fund - $193,466)

                                            Supplemental Appropriation Required

                       Appropriation Not Required.

Does this legislation require use of an emergency clause?

        Yes

                     x                       No

 

Recommendation

Suggested Action

Staff recommends that Council approve this authorization for the City Manager to advertise, receive bids and award to the lowest and best bidder for the Darrow Road Park Cleaning Project.

Submitted by,

Thomas J. Sheridan, City Manager