File #: 15-132    Version: 1 Name:
Type: Resolution Status: Passed
File created: 8/3/2015 In control: City Council
On agenda: 9/1/2015 Final action: 9/1/2015
Title: A RESOLUTION AUTHORIZING THE CITY MANAGER TO EXECUTE A CHANGE ORDER TO THE CONTRACT WITH CATTS CONSTRUCTION UNDER THE 2015 CONCRETE REPLACEMENT AND OVERLAY PROGRAM; AND DECLARING AN EMERGENCY. Executive Summary: The State Route 8 roadway has experienced additional needed repairs in 2015 including concrete joints and concrete panel repairs along a specified area of SR 8 within the City of Hudson.
Sponsors: William A. Currin
Indexes: Engineering
Attachments: 1. CATTS Construction - Cost estimate, 2. 2015 Concrete Bid Tabulation, 3. Resolution No. 15-132
Related files: 15-56, 15-47, 15-4

Title

A RESOLUTION AUTHORIZING THE CITY MANAGER TO EXECUTE A CHANGE ORDER TO THE CONTRACT WITH CATTS CONSTRUCTION UNDER THE 2015 CONCRETE REPLACEMENT AND OVERLAY PROGRAM; AND DECLARING AN EMERGENCY.

Executive Summary:  The State Route 8 roadway has experienced additional needed repairs in 2015 including concrete joints and concrete panel repairs along a specified area of SR 8 within the City of Hudson.

Body

Legislative History

15-4 - Permission to Advertise
15-47 - Enter into contract with CATTS
15-56 - Execute a Change Order for the overlay of Warrensburg Circle

Purpose & Explanation

The 2015 Annual Concrete Replacement Program was awarded to CATTS Construction, Inc. earlier this year, in which the contract included approximately $120,000 in repairs to SR 8 that were completed earlier this summer.  Since the work was completed, additional repairs have arisen within other areas of the roadway and the Contractor has provided the City with the estimated cost to perform these repairs.  The City staff has reviewed the cost estimate for this work and the contractor is maintaining their unit prices from their bid this year.  There will be an additional cost for mobilization and maintenance of traffic.  The contractor’s work on SR 8 earlier this year was satisfactory and in our opinion these costs are fair.  Note: The repairs to SR 8 are the responsibility of the Municipality, and we will need to coordinate this work with the Ohio Dept. of Transportation on any closures or traffic delays.

CATTS Construction, Inc. proposal for the cost of the repairs (See attached estimate for Priority #1 repairs) = $ 190,877.20.  Staff is recommending an approximate 5% (4.78%) contingency for a total cost of the repairs = $ 200,000.00.

Timing Considerations

This change order to the current contract will be issued upon approval of this request and funding.

Fiscal Impact

                       Currently Budgeted

                     X                       Supplemental Appropriation Required ($200,000 - 430 fund)

                       Appropriation Not Required.

 

Recommendation

Suggested Action

Staff recommends approving this request for a change order to the 2015 Concrete Replacement and Overlay Program for CATTS Construction, Inc., including the immediate appropriation of the necessary funds.  We are also asking that an emergency clause be added to the legislation in order to have this work performed as soon as possible and prior to the inclement weather.  Work will be scheduled upon approval.

Submitted by,

Jane Howington, City Manager

Thomas J. Sheridan, PE, PS, City Engineer