Hudson logo
File #: 13-98    Version: 1 Name:
Type: Resolution Status: Passed
File created: 7/3/2013 In control: City Council
On agenda: 7/17/2013 Final action: 7/17/2013
Title: A RESOLUTION AUTHORIZING THE CITY MANAGER TO ENTER INTO AN AGREEMENT WITH THE CITY OF AKRON FOR FIRE HYDRANT INSTALLATION AND ROAD RESURFACING OF PORTIONS OF MIDDLETON AND DARROW ROADS AS PART OF THE AKRON WATER MAIN REHABILITATION PROJECT; AND DECLARING AN EMERGENCY. Executive Summary: As part of the M.O.A. the City of Hudson agrees to fund a portion of this project including the installation of 5 new hydrants along Middleton Road and the resurfacing portion of the project on Middleton Road from SR 91 to Stow Road and along the east edge of Darrow Road from Middleton Road to the Twinsburg Township line.
Sponsors: William A. Currin
Indexes: Engineering, Streets / Sidewalks
Attachments: 1. Resolution No 13-98
Title
A RESOLUTION AUTHORIZING THE CITY MANAGER TO ENTER INTO AN AGREEMENT WITH THE CITY OF AKRON FOR FIRE HYDRANT INSTALLATION AND ROAD RESURFACING OF PORTIONS OF MIDDLETON AND DARROW ROADS AS PART OF THE AKRON WATER MAIN REHABILITATION PROJECT; AND DECLARING AN EMERGENCY.
Executive Summary:   As part of the M.O.A. the City of Hudson agrees to fund a portion of this project including the installation of 5 new hydrants along Middleton Road and the resurfacing portion of the project on Middleton Road from SR 91 to Stow Road and along the east edge of Darrow Road from Middleton Road to the Twinsburg Township line.
Body
Legislative History
None
Purpose & Explanation
The City of Akron, Ohio has received formal bids for the above mentioned project in June 2013.  The lowest bidder on the project was Kenmore Construction Company, Inc. ($1,343,674.50).  The project includes the replacement of the waterline bolts approximately every 18 feet (600 trenches) along the waterline, backfill, fire hydrants and resurfacing/restoration.  As part of the M.O.A. the City of Hudson agrees to fund a portion of this project including the installation of 5 hydrants along Middleton Road and the resurfacing portion of the project on Middleton Road from SR 91 to Stow Road and along the east edge of Darrow Road from Middleton Road to the Twinsburg Township line.
The total cost of the City of Hudson's portion of this project is $371,513.50
The City of Hudson is requesting a 10% contingency on this project for any unforeseen issues including additional full depth repairs that may be needed following the proof roll and other miscellaneous unforeseen issues that may arise during construction.
Total amount requested = $408,664.85 ($371,513.50-base + $37,151.35-Contingency)
The City of Hudson was scheduled to resurface Middleton Road due to the pavement rating condition.
Timing Considerations
If the authorization is approved by Council, the City Manager will enter into the M.O.A. and the appropriation will be included in the 2nd Quarter Appropriation in July 2013 for the total amount.
Fiscal Impact
        Currently Budgeted
      X        Supplemental Appropriation Required
        Appropriation Not Required.
 
Recommendation
Suggested Action
Staff recommends that City Council approve the recommendation authorizing the City Manager to enter into a Memorandum of Agreement (M.O.A.) with the City of Akron, Ohio for the cost to install fire hydrants and resurfacing of the Middleton Road and Darrow Road Water Main Rehabilitation Project.  The City staff is also requesting that an emergency clause be added to the legislation in order to protect the public welfare and safety.
Submitted by,
Anthony J. Bales, City Manager
Scott N. Schroyer, Assistant City Manager
Thomas J. Sheridan, PE, PS, City Engineer