File #: TMP-7583    Version: 1 Name:
Type: Resolution Status: Agenda Ready
File created: 10/28/2024 In control: City Council Workshop
On agenda: 1/28/2025 Final action:
Title: A RESOLUTION AUTHORIZING THE CITY MANAGER TO ADVERTISE FOR COMPETITIVE BIDS AND TO ENTER INTO A CONTRACT FOR THE 10' TRAIL ALONG BOSTON MILLS ROAD BETWEEN EXECUTIVE PARKWAY AND LAKE FOREST DRIVE AND FOR A SIDEWALK ALONG LAKE FOREST DRIVE BETWEEN BOSTON MILLS ROAD AND ESSEX ROAD. Brief Description: The project includes the installation of a new 10' trail along Boston Mills Road starting at the existing trail west of Omni Lake Parkway and extending east to Lake Forest Drive and a new 5-foot wide sidewalk along the east side of Lake Forest Drive between Boston Mills Road and Essex Road. The project will also include the realignment of the intersection of Boston Mills Road and Lake Forest Drive.
Sponsors: Jeffrey L. Anzevino
Indexes: Engineering, Streets / Sidewalks
Attachments: 1. Boston Mills Trail Exhibit, 2. Lake Forest Drive Exhibit, 3. Draft Resolution
Related files: 24-0051

Title

A RESOLUTION AUTHORIZING THE CITY MANAGER TO ADVERTISE FOR COMPETITIVE BIDS AND TO ENTER INTO A CONTRACT FOR THE 10’ TRAIL ALONG BOSTON MILLS ROAD BETWEEN EXECUTIVE PARKWAY AND LAKE FOREST DRIVE AND FOR A SIDEWALK ALONG LAKE FOREST DRIVE BETWEEN BOSTON MILLS ROAD AND ESSEX ROAD.

Brief Description:   The project includes the installation of a new 10’ trail along Boston Mills Road starting at the existing trail west of Omni Lake Parkway and extending east to Lake Forest Drive and a new 5-foot wide sidewalk along the east side of Lake Forest Drive between Boston Mills Road and Essex Road. The project will also include the realignment of the intersection of Boston Mills Road and Lake Forest Drive.

Body

Legislative History

24-0051 - Discussion regarding alignment of sidewalk along Lake Forest Drive

Purpose & Explanation

10’ Trail along Boston Mills Road

This project’s design, by Euthenics Inc, is anticipated to be completed in early 2025.  The project includes a 3,500-foot-long, 10-foot-wide asphalt trail, boardwalk, and bridge project along the north side of Boston Mills Road. The trail will begin at the existing asphalt path west of Omni Lake Parkway and extend eastward to Lake Forest Drive.

The project will connect to Boston Mills Park, incorporating a stone loop within the park, a boardwalk, and a bridge over Lake Forest. Additional improvements include paving of the Park’s parking lot, storm drainage, grading, crosswalks, lighting, electric conduits, driveways, tree  clearing and restoration.

The project also includes new crosswalks with Rectangular Rapid Flashing Beacons (RRFBs) on Boston Mills Road at Westpoint Drive and Ridgewood Boulevard.  See exhibit attached.

Staff anticipates securing an ODNR grant in the amount of $250,000 for the bridge over Lake Forest.

The estimated total cost of construction, including a 10% contingency, is $2,500,000. The City will seek additional City Council approval if costs exceed this amount.

Lake Forest Sidewalk and Realignment of Boston Mills/Lake Forest Drive Intersection


The proposed sidewalk installation along Lake Forest Drive (Boston Mills Road to Essex Road) is currently budgeted for construction in 2025 as part of the Connectivity Program.  

The original project alignment included a mid-block crosswalk on Lake Forest Drive at Chadborne Drive.  This was due to the skewed intersection of Lake Forest Drive at Boston Mills Road creating a very long crosswalk with poor sitelines.  Based upon public input and review by staff, Lake Forest Drive at Boston Mills Road will be realigned to a more traditional 90-degree intersection, limiting the crosswalk distance, creating a safer pedestrian crossing and eliminating the mid-block crossing at Chadborne Drive.  See attached exhibit.

The sidewalk project and road intersection realignment are being designed in-house and based upon public input; the proposed sidewalk alignment will be along the easterly side of Lake Forest Drive from Boston Mills Road to Essex Road.
  The sidewalk construction also includes storm drainage improvements, grading, crosswalks, lighting, electric conduits, driveways, and minor clearing and restoration.

The estimated total cost of construction is $550,000, which includes a 10% contingency. The City will return to City Council if the cost exceeds the above total cost of the project. 

The trail project along Boston Mills Road, sidewalk along Lake Forest Drive and intersection realignment projects are anticipated to be bid together and awarded in early 2025 and constructed in the spring/summer, 2025.

 

Legal Authority for Proposed Legislation

Pursuant to Charter Section 6.04:

                     X                       Competitively bid and advertised for three consecutive weeks

                       Joint or Cooperative Purchase Program

                       Professional Services

                                            Other

Fiscal Impact

                     X                       Currently Budgeted (10’ Trail - 2025 Budget - 205 Parks fund - $2,500,000; Lake Forest - 430 Fund - $550,000)

         Supplemental Appropriation Required

                          Appropriation Not Required

 

 

Does this legislation require use of an emergency clause?

__ Yes

_X__No

 

Recommendation

Suggested Action

Staff recommends that City Council approve this authorization for the City Manager to advertise, receive bids, and enter into a contract for the installation of a 10’ trail along Boston Mills Road between Executive Parkway and Lake Forest Drive and a sidewalk along Lake Forest Drive between Boston Mills Road and Essex Road,

Submitted by,

Thomas J. Sheridan, City Manager
Trent Wash, Assistant Public Works Director
Bradley S. Kosco, PE, PS, City Engineer
David Rapp, PE, PS, Assistant City Engineer
Jonathon Szalay, PE, SI, Senior Engineer