File #: 25-156    Version: 1 Name:
Type: Resolution Status: Passed
File created: 9/12/2025 In control: City Council
On agenda: 10/7/2025 Final action: 10/7/2025
Title: A RESOLUTION AUTHORIZING THE CITY MANAGER TO ADVERTISE FOR COMPETITIVE BIDS AND TO ENTER INTO A CONTRACT FOR THE CONSTRUCTION OF THE HUDSON PUBLIC WORKS FACILITY PROJECT; AND DECLARING AN EMERGENCY. Brief Description: This project involves comprehensive site preparation, infrastructure development, and the construction of the Hudson Public Works Facility, along with new storage facilities.
Sponsors: Jeffrey L. Anzevino
Indexes: Public Works - Administration, Public Works - Public Properties
Attachments: 1. Resolution No. 25-156
Related files: 25-131, 24-114, 23-82, 23-116, 24-80

Title

A RESOLUTION AUTHORIZING THE CITY MANAGER TO ADVERTISE FOR COMPETITIVE BIDS AND TO ENTER INTO A CONTRACT FOR THE CONSTRUCTION OF THE HUDSON PUBLIC WORKS FACILITY PROJECT; AND DECLARING AN EMERGENCY.

Brief Description:  This project involves comprehensive site preparation, infrastructure development, and the construction of the Hudson Public Works Facility, along with new storage facilities.

Body

Legislative History

Ordinance No. 23-82 authorized the purchase of the Hudson Drive parcels for $1,900,000

Ordinance No. 23-116 authorized the issuance of $1,900,000 in notes for the purchase of the land

Ordinance No. 24-80 authorized the contract with Brandstetter Carroll, Inc for the design of the new facility

Ordinance 24-114 authorized the issuance of $3,295,000 in notes for the purchase of land and cost of design of the new facility

Ordinance 25-131 an ordinance providing for the issuance and sale of not to exceed $31,000,000 of notes, in anticipation of bonds, for the purpose of paying costs of construction, furnishing and equipping a facility.

Purpose & Explanation

In 2023, City Council authorized the City Manager to acquire property on Hudson Drive for the development of a dedicated facility. Subsequently, in 2024, the City Manager was authorized to enter into a professional services agreement for the design of the new Public Works Facility.

Over the past year, City staff have collaborated closely with the design firm to optimize the operational efficiency of the proposed facility. The final design for the Hudson Public Works Facility Project has been completed and received formal approval from the Hudson Planning Commission

With Council approval, the staff seeks legislation authorizing the City Manager to publicly bid for and award a construction contract for the project. 

Budget Amount- $30,913,768.00  (Construction)

Contingency Amount- $1,081,980.00

Total Project cost with 3.5% Contingency - $31,996,288.00

The Public Works Facility expense would be applied to the following funds, General Fund: $24,894,587.00, Electric Fund $4,350,640.00, Water Fund $2,751,061.00.

Legal Authority for Proposed Legislation

Pursuant to Charter Section 6.04, Contracts & Purchasing:

  X                       Competitively bid and advertised for two consecutive weeks; bid tab attached: [Yes/No/NA])

                       Joint or Cooperative Purchase Program

                       Professional Services

                       Other [provide explanation]

Fiscal Impact

  X                       Currently Budgeted (Account-)

                         Supplemental Appropriation Required

                       Appropriation Not Required

Does this legislation require use of an emergency clause?

X                       Yes [Due to timing constraints]

                          No

 

Recommendation

 

Suggested Action

Staff recommends the City Council approve this legislation authorizing the City Manager to publicly bid and award a construction contract for the project  to the lowest and best bidder not to exceed the budgeted amount including the contingency.   

Submitted by,

Thomas J. Sheridan, City Manager

Kevin Powell, Public Works Director

Eric Hutchinson, Assistant Public Works Director