Hudson logo
File #: 23-64    Version: Name:
Type: Resolution Status: Passed
File created: 4/11/2023 In control: City Council
On agenda: 5/2/2023 Final action: 5/2/2023
Title: A RESOLUTION AUTHORIZING THE CITY MANAGER TO ENTER INTO A CONTRACT WITH TK ELEVATOR CORPORATION FOR THE CITY HALL ELEVATOR IMPROVEMENT PROJECT. Brief Description: The project will include the replacement of the operating components of the existing elevator at City Hall. These components include the car controller, car switches and panels, door interlocks, emergency systems, and the communication system as well as required electrical and HVAC upgrades.
Sponsors: Jeffrey L. Anzevino
Indexes: Public Works - Public Properties
Attachments: 1. City Hall Project Financial Exhibit A, 2. City Hall Projects Summary 4-26-23, 3. Resolution No. 23-64
Related files: 24-97
Title
A RESOLUTION AUTHORIZING THE CITY MANAGER TO ENTER INTO A CONTRACT WITH TK ELEVATOR CORPORATION FOR THE CITY HALL ELEVATOR IMPROVEMENT PROJECT.
Brief Description: The project will include the replacement of the operating components of the existing elevator at City Hall. These components include the car controller, car switches and panels, door interlocks, emergency systems, and the communication system as well as required electrical and HVAC upgrades.
Body
Legislative History
None.
Purpose & Explanation
The City Hall remodel project did not include funding for the elevator which is believed to be original to the building. Since using City Hall over the last several years, staff have worked to improve the reliability and durability of the elevator. Unfortunately, the elevator remains unreliable. Upgrades will improve fire and safety features while decreasing user wait times. There will also be a decrease in energy consumption and reduced operational costs.

In June 2022, staff invited two vendors to provide pricing on the improvement project. The vendors provided a price of approximately $80,000 and this amount was included in the 2023 budget. During the project planning stage, staff were notified that due to the age of the unit, the entire elevator and all controls must be brought up to current code standards. This increase in project scope will also include required electrical work to add lighting in the elevator pit area, new disconnect switches, electrical upgrades in the mechanical room, and HVAC improvements in the mechanical room. A fire-rated door will also be added to the mechanical room.

Elevator Modernization Project Budget $80,000.00
TK Elevator Bid : $156,641.00
10% Contingency: $15,664.10
Total Project Cost: $172,305.10

Additional Funds Allocated: $92,305.10

Pricing for the project is provided via Sourcewell cooperative purchasing program.