A discussion and update on the S. Main Street Improvement Project (PID 106445) regarding the preliminary design of the S. Main Street Safety Improvement Project.
Executive Summary: The Engineering Staff has been working with AMATS and ODOT on the scope of the project over the past several months. Staff will be discussing the project and update Council on the status and tentative design. We are still awaiting some information from our Consultant and ODOT and additional documents will be presented to Council at the meeting.
Body
Legislative History
16-0123 - Discussion regarding S. Main Street Safety Study
17-105 - Affirming Submission of an Application for CMAQ Funds
18-97 - Enter into an Agreement with GPD Group for Preliminary Engineering Design and Study Services
Purpose & Explanation
Staff will be updating City Council and the Mayor on the status of the S. Main St. Project and discussing the scope of the project.
Timing Considerations
Following the discussion with City Council, staff will proceed with the preliminary design of the project and update City Council and the Mayor in the near future on the progress of the project.
Fiscal Impact
X Currently Budgeted
Supplemental Appropriation Required
Appropriation Not Required.
Recommendation
Suggested Action
Staff is seeking Council’s direction on how they would like staff to proceed.
Submitted by,
Jane Howington, City Manager
Thomas J. Sheridan, PE, PS, Assistant City Manager - Professional Services
Bradley S. Kosco, PE, PS, City Engineer