Hudson logo
File #: 17-0043    Version: 1 Name:
Type: Staff Report Status: Filed
File created: 5/2/2017 In control: City Council Workshop
On agenda: 5/9/2017 Final action: 5/9/2017
Title: Discussion Regarding Barlow Road Path/Walk Improvements Executive Summary: Staff would like to update Council on the design of the Barlow Road Path/Walk Improvements.
Sponsors: David A. Basil
Attachments: 1. Barlow Road Exhibits
Title
Discussion Regarding Barlow Road Path/Walk Improvements
Executive Summary: Staff would like to update Council on the design of the Barlow Road Path/Walk Improvements.
Body
Legislative History
15-68 - Enter into a design contract with GPD Group
15-0010 - Discussion regarding design options was held on January 27, 2015.
16-0020 - Discussion regarding Barlow Road Improvements and Barlow/Terex Road Intersection
16-68 - Permission to Advertise, Bid and Award the Barlow Road Widening Project, Phase I
16-117 - Acquisition of Land at 1170 Barlow Road
16-135 - Permission to Advertise, Bid and Award the Barlow Road Railroad Profile Grade Change, Phase II
16-154 - Permission to Advertise, Bid and Award the Barlow Road / Terex Road Intersection Improvements, Phase III
Purpose & Explanation
Below is the outline for discussion:
* Existing conditions - roadside ditches, drives, 60' R/W (30' per side), 23' pavement (11.5' per side) leaving 18' for path/walk and ditch, trees
* Proposed Project:
o Metro Parks Hike & Bike Path to Terex Road, 10' path connecting to hike and bike path at south west quadrant of Terex and Barlow Road
* Signalized Ped Crossing at Terex Road
* Asphalt Surface
o Terex Road to East side of old Flood Company Parcels, 7' Path
* Crosses Reserve Lane, Williamsburg Circle, Nicholson Drive
* Portion of curb added along Hole #9
* Asphalt Surface
o East side of old Flood Company Parcels to SR 91, 5' Path
* Crosses Holland Drive
* Concrete Surface
Additional Considerations:
* Public Meeting
* Right-of-way impacts 32 work agreements
* Tree impacts 95+/-; proposed landscaping
* Drive impacts 30+/-
* Drainage/Swales
* Bike use = "sharrows" and path
* ODNR Grant
* Connection to Veterans Trail Phase 3
* Budget
* Schedule
Timing Considerations
A public open house will be held in the coming months with construction anticipated for 2018.
Fiscal Impact
Currently Budgeted
Supplemental Appropriation Required
Appropriation Not Required.

Recommendation
S...