Sidewalk and Trail Master Plan update and possible next phase of the Connectivity Plan.
Brief Description: Review of the current status of the 2021-2025 Connectivity Plan project and preliminary discussion regarding future plan update and applicable projects.
Body
Legislative History
Res No. 21-8 - Adopted in Concept the Sidewalk and Trail Master Plan 2021-2025; 2/16/2021
Purpose & Explanation
Please see the attached information tracking the current status of the 2021-2025 Master Plan and a map noting future connections to consider for study with the next plan update.
Staff recommends Council proceed with a formal plan update in 2024. Council could consider another round of community meetings/engagement in Jan-March 2024. This timing would allow the key findings of the Draft Comprehensive Plan to be established. Additionally, completion of a sidewalk and trail master plan by second quarter 2024 will allow recommendations to be incorporated with the budget discussion to occur in the second half of 2024.
Timing Considerations
None
Fiscal Impact
Currently Budgeted (Account #, $)
Supplemental Appropriation Required (Account #, $)
Appropriation Not Required.
Recommendation
Suggested Action
Staff recommends City Council review the current project status and provide direction regarding a future sidewalk and trail plan update in 2024.
Submitted by,
Thomas J. Sheridan, City Manager
Bradley Kosco, City Engineer
Greg Hannan, Community Development Director