Tinkers Creek Watershed Study - Model and Final Draft Report
Brief Description: Staff and the City’s consultant, ms consultants, will present the Tinkers Creek Watershed Study development, findings and recommendations.
Body
Legislative History
Res No 25-58 - Professional Services Contract with ms consultants; 4/8/2025
Purpose & Explanation
The Tinker’s Creek Watershed Study evaluated the local stormwater system, specifically examining major streams, ponds, bridges, culverts, and trunk sewer mains.
The project aimed to create a detailed inventory of existing infrastructure while developing an updated hydrologic and hydraulic model. These tools were used to identify and prioritize solutions for major flooding issues and, where feasible, improve overall water quality. Findings from the study were recently shared during a public meeting at Hudson High School on April 23 and are now set for presentation to City Council. Once Council reviews the findings, the report will be finalized to serve as a foundation for future capital budget planning.
Fiscal Impact
Currently Budgeted
Supplemental Appropriation Required
Appropriation Not Required.
Recommendation
Suggested Action
Staff will review the study to date, answer questions and collect any Council feedback.
Submitted by,
Thomas J. Sheridan, City Manager
Brian Griffith, Assistant City Manager
Bradley S. Kosco, PE, PS, City Engineer
David Rapp, PE, PS, Assistant City Engineer