Hudson logo
File #: 20-165    Version: 1 Name:
Type: Resolution Status: Passed
File created: 11/30/2020 In control: City Council
On agenda: 12/15/2020 Final action: 12/15/2020
Title: A RESOLUTION AUTHORIZING THE CITY MANAGER TO SUBMIT THE STATE ROUTE 91 SOUTH SAFETY IMPROVEMENT PROJECT (PID 106445) PLAN TO THE HUDSON PLANNING COMMISSION FOR REPORT AND RECOMMENDATION PURSUANT TO CHARTER SECTION 9.02. Brief Description: The SR 91 South Safety Improvement Project design limits are on SR 91 (S. Main Street) from Barlow Road to the Stoney Hill Drive intersection. The project includes widening of the roadway for bike lanes and new center turn lane. Per the City Charter, Section 9.02 - Planning Commission - Powers and Duties, the street widening project shall be submitted to the Planning Commission for report and recommendation.
Sponsors: Craig Shubert
Indexes: Engineering
Attachments: 1. Preliminary Design Plan Exhibit 11-16-20, 2. Resolution No. 20-165, 3. Packet to Council - S Main Street 2-26-2021
Related files: 18-97, 18-0101, 20-22, 18-186, 17-105, 21-138, 21-122, 21-30, 21-139, 21-153, 21-154, 22-40
Title
A RESOLUTION AUTHORIZING THE CITY MANAGER TO SUBMIT THE STATE ROUTE 91 SOUTH SAFETY IMPROVEMENT PROJECT (PID 106445) PLAN TO THE HUDSON PLANNING COMMISSION FOR REPORT AND RECOMMENDATION PURSUANT TO CHARTER SECTION 9.02.
Brief Description: The SR 91 South Safety Improvement Project design limits are on SR 91 (S. Main Street) from Barlow Road to the Stoney Hill Drive intersection. The project includes widening of the roadway for bike lanes and new center turn lane. Per the City Charter, Section 9.02 - Planning Commission - Powers and Duties, the street widening project shall be submitted to the Planning Commission for report and recommendation.
Body
Legislative History
16-0123 - Discussion regarding S. Main Street Safety Study
17-105 - Affirming Submission of an Application for CMAQ Funds
18-0101 - Discussion and Update on the S. Main Street Improvement Project
18-97 - Authorize Preliminary Engineering Design Contract with GPD Group
18-186 - Enter into LPA Agreement with ODOT
20-22 - Authorize Final Engineering Design Contract with GPD Group
Purpose & Explanation
The project limits are on SR 91 (S. Main Street) from Barlow Road to the Stoney Hill Drive intersection. The project is being partially funded via an ODOT Safety Program Grant and AMATS CMAQ grant. The project goal is to implement four countermeasures outlined in the State Route 91 Safety Study submitted and approved by ODOT in 2016, as follows:

1. Widen SR 91 to accommodate a center two-way left turn lane throughout the project area.
2. Resurface the SR 91 corridor throughout the length of the project limits.
3. Construct 5' bike lanes on the east and west side of SR 91.
4. Construct sidewalks on the east and west side of SR 91.

To retain the federal and state funding secured for the project, the final design must incorporate these four countermeasures. The new roadway section will consist of three - 11 ft. wide lanes (2 thru lanes and one center turn lane), 5-foot on-street bike lanes o...

Click here for full text