AN ORDINANCE ACCEPTING DEDICATION OF THE PUBLIC STREETS, EASEMENTS AND PUBLIC IMPROVEMENTS WITHIN THE SEASONS GREENE ECO-INDUSTRIAL PARK SUBDIVISION. (as revised 11/21/2017)
Executive Summary: The developer of Seasons Greene Eco-Industrial Park has completed public improvements within the subdivision and is requesting that City Council accept the dedication of these improvements and right-of-way.
Body
Legislative History
Preliminary Subdivision Plan approval on January 10, 2011; PC Case 2010-05.
Improvement Plan Authorization approved on February 28, 2008; PC Case 2011-08.
Final Plat approval on September 14, 2015; PC Case 2015-22.
Purpose & Explanation
The ordinance will accept the dedication of rights-of-way, easements, and public improvements for Seasons Greene Eco-Industrial Park. The City Solicitor advises that acceptance of dedication of subdivisions should be approved by ordinances of City Council.
The City Engineer’s office has inspected the subdivision and has found that the improvements have been installed according to approved plans and City standards. The only remaining item to be performed by the developer is the installation of the street trees, and the developer has deposited the necessary funds with the City to install the street trees. Council acceptance will transfer the right-of-way to the City of Hudson and will return deposits to the developer. A two-year maintenance bond has been received from the developer.
Timing Considerations
None.
Fiscal Impact
Currently Budgeted
Supplemental Appropriation Required
X Appropriation Not Required.
Recommendation
Suggested Action
It is recommended that City Council approve the ordinance accepting for dedication the right-of-way and public improvements for Seasons Greene Eco-Industrial Park.
Submitted by,
Jane Howington, City Manager
Thomas J. Sheridan, PE, PS, Assistant City Manager - City Engineer
Greg Hannan, City Planner