A RESOLUTION AUTHORIZING THE CITY MANAGER TO ENTER INTO A PROFESSIONAL SERVICES CONTRACT WITH TRANSYSTEMS FOR ENGINEERING DESIGN SERVICES FOR THE STOW ROAD AND MIDDLETON ROAD TRAFFIC SIGNAL IMPROVEMENT PROJECT.
Brief Description: This legislation would retain TranSystems for the design of the Stow Road and Middleton Road Traffic Signal Improvement Project.
Body
Legislative History
None
Purpose & Explanation
In early 2021, an intersection safety study was performed on the intersection of Stow Road and Middleton Road and found that a new signal is warranted.
A Request for Proposal for the design of the signal improvement was sent out to five (5) engineering firms. Two (2) firms submitted a proposal for the signal improvement design. The firms were Mott MacDonald and TranSystems. Based on the review of the proposals, staff identified the best consultant is TranSystems at a design fee of $64,568.28. This fee includes the surveying, design, utility coordination, right-of-way acquisition and bid/construction support services.
Note: The right-of-way acquisition is required due to exiting property lines adjacent to intersection (see exhibit attached) and need for right-of-way to place new pole foundations.
As with other professional services contracts we are requesting a 10% contingency to handle any minor changes in the scope of services that may occur during the course of the design. The 10% amount would be $6,456.28 for a total fee of $71,025.11. For considerations in excess to this amount, we will return to the City Council
Construction of the traffic signal is estimated to be the summer 2022.
Legal Authority for Proposed Legislation
Pursuant to Charter Section 6.04, Contracts & Purchasing:
Competitively bid and advertised for two consecutive weeks
Joint or Cooperative Purchase Program
X Professional Services
Other
Fiscal Impact
X Currently Budgeted (430 account - $71,026)
Supplemental Appropriation Required
Appropriatio...