Title
A RESOLUTION AUTHORIZING THE CITY MANAGER TO EXECUTE A CHANGE ORDER TO THE CONTRACT WITH THOMPSON ELECTRIC INC. FOR CONSTRUCTION SERVICES FOR THE EASTSIDE SUBSTATION TRANSFORMER REPLACEMENT PROJECT; AND DECLARING AN EMERGENCY.
Brief Description: This project involves the completion of the required construction services to install the transformer, voltage regulators and related equipment needed to complete this project.
Body
Legislative History
Res: 20-162 A Resolution authorizing the City Manager, during the year 2021, to advertise for bids or to utilize the various charter authorize governmental competitive purchasing program
Res: 22-66 A Resolution authorizing the City Manager to bid and award contracts for the Eastside Substation Transformer Replacement Project.
Res: 23-78 A Resolution authorizing the City Manager to enter into a contract with Thompson Electric Inc. for constructions services for the Eastside Substation Transformer Replacement Project
Purpose & Explanation
The Eastside Substation Transformer Replacement project began in Q2 2021, with GPD handling the design work and key components procured in Q4 2021. Delivery estimates for major components were originally set for Q3 2022 but were delayed due to unforeseen issues with material supplies, design adjustments, ordering, and shop submittals.
Through the bidding process, we secured a contractor to install equipment and materials as they became available. During the final installation phase, it was discovered that the bus duct components were obsolete and could not be retrofitted to integrate with the new gear. Consequently, a new section of bus duct must be manufactured and installed. Thompson Electric has submitted a proposed change order for $51,218.47 to fabricate and install the replacement bus duct.
The City Administration is requesting City Council approval to authorize the City Manager to execute a change order to a contract with Thompson Electric Inc for the Eastside Substation Tr...
Click here for full text