Hudson logo
File #: 24-95    Version: 1 Name:
Type: Resolution Status: Passed
File created: 7/22/2024 In control: City Council
On agenda: 8/20/2024 Final action: 8/20/2024
Title: A RESOLUTION AMENDING RESOLUTION NO. 20-58 TO INCREASE THE PROJECT COST FOR THE RESURFACING OF RAVENNA ROAD BETWEEN OLD MILL ROAD AND THE PORTAGE COUNTY LINE AND AUTHORIZE THE CITY MANAGER TO ENTER INTO A REVISED AGREEMENT WITH THE COUNTY OF SUMMIT FOR COOPERATION AND COST SHARING; AND DECLARING AN EMERGENCY. Brief Description: The City's initial project cost was $90,750, however due to increased construction costs the City's portion has increased to $313,252.21. The increase in cost from 2019 is due to inflation since the Covid pandemic. This project is for the resurfacing of Ravenna Road from Old Mill Road to the Portage County Line. Approximately 0.75 miles of this stretch of roadway is within the City of Hudson.
Sponsors: Jeffrey L. Anzevino
Indexes: Engineering
Attachments: 1. Location Map, 2. Resolution No. 24-95
Related files: 20-58
Title
A RESOLUTION AMENDING RESOLUTION NO. 20-58 TO INCREASE THE PROJECT COST FOR THE RESURFACING OF RAVENNA ROAD BETWEEN OLD MILL ROAD AND THE PORTAGE COUNTY LINE AND AUTHORIZE THE CITY MANAGER TO ENTER INTO A REVISED AGREEMENT WITH THE COUNTY OF SUMMIT FOR COOPERATION AND COST SHARING; AND DECLARING AN EMERGENCY.
Brief Description: The City's initial project cost was $90,750, however due to increased construction costs the City's portion has increased to $313,252.21. The increase in cost from 2019 is due to inflation since the Covid pandemic. This project is for the resurfacing of Ravenna Road from Old Mill Road to the Portage County Line. Approximately 0.75 miles of this stretch of roadway is within the City of Hudson.
Body
Legislative History
None.
Purpose & Explanation
In 2019, Summit County applied for, and was awarded an Akron Metropolitan Area Transportation Study (AMATS) Federal Surface Transportation Block Grant (STBG) funds in the amount of $600,000 towards the resurfacing of the portion of Ravenna Road from Old Mill Road to the Portage County Line.
The project's total construction cost was estimated by the County at $750,000 and the $600,000 grant is being split between the County and City towards the construction of the project. Any costs above the grant are the responsibility of the County and City. The total project length is 1.36 miles of which approximately 0.75 miles (55% of project length) is in the City of Hudson. The project includes resurfacing, base repairs, and replacement of pavement markings.
The project's construction was planned for 2025; however AMATS identified that grant funds were available to move the project construction into 2024.
The City's portion of the original construction cost estimate was $95,000. This was identified by taking the original construction cost estimate of $750,000, minus grant funding of $600,000 leaving a balance of $150,000. The County/City would split the construction cost leaving the City...