File #: 26-8    Version: 1 Name:
Type: Resolution Status: Passed
File created: 12/29/2025 In control: City Council
On agenda: 1/20/2026 Final action: 1/20/2026
Title: A RESOLUTION AUTHORIZING THE CITY MANAGER TO ADVERTISE FOR COMPETITIVE BIDS AND TO ENTER INTO A CONTRACT FOR THE FRANKLIN STREET WATERLINE AND SIDEWALK INSTALLATION PROJECT. Brief Description: The project includes the installation of a new 5-foot wide sidewalk along the west side of Franklin Street and the replacement of the waterline between Aurora Street and the Middle School.
Sponsors: Jeffrey L. Anzevino
Indexes: Engineering
Attachments: 1. Exhibit Franklin St Sidewalk and Water Main, 2. Resolution No. 26-8
Related files: 25-148
Title
A RESOLUTION AUTHORIZING THE CITY MANAGER TO ADVERTISE FOR COMPETITIVE BIDS AND TO ENTER INTO A CONTRACT FOR THE FRANKLIN STREET WATERLINE AND SIDEWALK INSTALLATION PROJECT.
Brief Description: The project includes the installation of a new 5-foot wide sidewalk along the west side of Franklin Street and the replacement of the waterline between Aurora Street and the Middle School.
Body
Legislative History
Ord No 25-148 - Accepting Dedication of the Public Street and Easements; 10/7/2025
Purpose & Explanation
Franklin Street Sidewalk

To improve safety for students and pedestrians walking to and from the Middle School, City staff commenced with the design of a new sidewalk along Franklin Street. Due to the south portion of the sidewalk being on school property, the City will be entering into a Cost Share Agreement with the Schools with the schools and to reimburse the City for this portion of the sidewalk for a total cost with contingency of $28,000.00 under a separate legislative item.

The estimated total cost of construction for the entire sidewalk length is $125,000 ($97,000 - City portion + $28,000 - School portion), which includes a 10% contingency. Staff will return to City Council to seek additional funding, if costs exceed this cost estimate amount.

Franklin Street Waterline

This work includes the replacement of a failing, 6" water main with a new 8" water main along Franklin Street between Aurora Street and the end of Franklin Street where it enters school property.

The estimated total cost of the waterline replacement is $275,000, which includes a 10% contingency.

The sidewalk and waterline project were designed in-house and will be bid together as one project. Once the work is completed the roadway will be resurfaced under the 2026 Asphalt Resurfacing Program later this fall.
All construction work will take place in the summer when school is not in session.