File #: 20-9    Version: 1 Name:
Type: Resolution Status: Passed
File created: 1/6/2020 In control: City Council
On agenda: 2/4/2020 Final action: 2/4/2020
Title: A RESOLUTION AUTHORIZING THE CITY MANAGER TO ENTER INTO A CONTRACT WITH ENVIRONMENTAL DESIGN GROUP FOR PROFESSIONAL SERVICES FOR THE DESIGN OF THE BARLOW COMMUNITY CENTER DAM IMPROVEMENTS. Brief Description City staff requested ten (10) consultants submit a proposal for the design of the Barlow Community Center Dam Improvements Project. A total of eight (8) consultants submitted proposals, and Environmental Design Group (EDG) was selected as the consultant with the best design proposal and fee.
Sponsors: Craig Shubert
Indexes: Engineering, Finance - Appropriations and Budget
Attachments: 1. BCC Improvements Exhibits, 2. Resolution No. 20-9
Related files: 19-79, 17-202, 22-21
Title
A RESOLUTION AUTHORIZING THE CITY MANAGER TO ENTER INTO A CONTRACT WITH ENVIRONMENTAL DESIGN GROUP FOR PROFESSIONAL SERVICES FOR THE DESIGN OF THE BARLOW COMMUNITY CENTER DAM IMPROVEMENTS.
Brief Description City staff requested ten (10) consultants submit a proposal for the design of the Barlow Community Center Dam Improvements Project. A total of eight (8) consultants submitted proposals, and Environmental Design Group (EDG) was selected as the consultant with the best design proposal and fee.
Body
Legislative History
17-202 - Authorized Feasibility Study with Arcadis, US, Inc.; 12/27/2017
19-79 - Enter into Cost Share Agreement with NEORSD; 5/21/2019
Purpose & Explanation
In April 2017, the Ohio Department of Natural Resources (ODNR), Division of Water Resources, inspected both the Upper and Lower Lake Dams at the Barlow Community Center. ODNR identified that both dams require improvements to the primary spillways and emergency overflows in order to meet the updated design criteria as designated by the Ohio Administrative Code.

In March 2019, City of Hudson, in association with the Northeast Ohio Regional Sewer District (NEORSD) finalized a study titled the "Cuyahoga River South (CRS),
Stormwater Master Plan (SWMP) - City of Hudson Community Report". The CRS SWMP
study identified problems and recommend stormwater solutions, within the Brandywine Creek Watershed, to improve regional storm water management and water quality in the watershed. The study recommended improvements to the Barlow Community Center's Upper Lake, including increased storm detention volume and operational controls.

In April 2019, the City's and its consultant finalized the "Feasibility Study for the Barlow Community Center Dams". The feasibility study developed a set of alternative design solutions to meet the ODNR dam requirements and verified that the additional storage volume identified in the CRS SWMP can be constructed.

In May 2019, NEORSD confirmed that it w...