File #: 15-87    Version: 1 Name:
Type: Resolution Status: Passed
File created: 3/26/2015 In control: City Council
On agenda: 6/16/2015 Final action: 6/16/2015
Title: A RESOLUTION PURSUANT TO OHIO REVISED CODE 5521.01 CONSENTING TO THE DIRECTOR OF THE OHIO DEPARTMENT OF TRANSPORTATION TO COMPLETE A NOISEWALL PROJECT (PID NO. 98622) WITHIN THE CITY OF HUDSON, AUTHORIZING THE CITY OF HUDSON TO SERVE AS THE LOCAL PUBLIC AGENCY, AUTHORIZING FUNDS THEREFOR, AND DECLARING AN EMERGENCY. Executive Summary: ODOT is required to request and receive legislation from the City of Hudson prior to making any repairs to State Highways within the corporate limits of the municipality.
Sponsors: William A. Currin
Indexes: Engineering
Attachments: 1. ODOT Participatory Legislation for Noisewall Project, 2. Resolution No. 15-87
Related files: 16-156
Title
A RESOLUTION PURSUANT TO OHIO REVISED CODE 5521.01 CONSENTING TO THE DIRECTOR OF THE OHIO DEPARTMENT OF TRANSPORTATION TO COMPLETE A NOISEWALL PROJECT (PID NO. 98622) WITHIN THE CITY OF HUDSON, AUTHORIZING THE CITY OF HUDSON TO SERVE AS THE LOCAL PUBLIC AGENCY, AUTHORIZING FUNDS THEREFOR, AND DECLARING AN EMERGENCY.
Executive Summary: ODOT is required to request and receive legislation from the City of Hudson prior to making any repairs to State Highways within the corporate limits of the municipality.
Body
Legislative History
None.
Purpose & Explanation
ODOT is required to request and receive legislation from the City of Hudson prior to making any repairs to State Highways within the corporate limits of the municipality. This request is for the installation of a noise wall along I-80 (Ohio Turnpike) within the corporation limits of the City of Hudson. The wall will be constructed within the property limits (R/W of the Turnpike). The limits of the work will be along a portion of Jesse Drive.
The City of Hudson will be required to participate with a local share - not to exceed cost of $145,000.00. The Turnpike Mitigation Grant in which the City of Hudson applied in 2014 will finance the remaining portion of the project. The estimated cost of the project in 2014 = $1,200,000. This is not a LPA project and Hudson will not be overseeing the design or construction. The project is currently under design by ODOT. The work is planned for construction in 2017-18.
Timing Considerations
The agreement will be executed once it has been approved by City Council.
Fiscal Impact
Currently Budgeted
Supplemental Appropriation Required
X Appropriation Not Required. (2019 Budget)

Recommendation
Suggested Action
Staff recommends that City Council approve this Resolution authorizing the City Manager to enter into an agreement with the State of Ohio Department of Transportation and we ask that an emergency clause be added to the legislati...