Hudson logo
File #: 17-0054    Version: 1 Name:
Type: Staff Report Status: Filed
File created: 5/30/2017 In control: City Council
On agenda: 6/13/2017 Final action: 6/13/2017
Title: A presentation and discussion of the feasibility of installing a photovoltaic solar power system on a portion of the former YDC property. Executive Summary: In the first quarter of 2017 City Council requested information on the feasibility of installing a solar power system to Hudson's municipal electric distribution system to help offset a portion of the City's overall power purchases. The City's electric system consultant Mr. John Courtney of Courtney & Associates will present information regarding the potential advantages of installing such a system, the pricing we would expect to see per KWh, and the potential offsets in power, transmission and capacity costs.
Indexes: Public Works - Electric
Attachments: 1. Solar Array Site - Map, 2. Solar System Location - Map, 3. Hudson Solar Presentation
Related files: 18-122

Title

A presentation and discussion of the feasibility of installing a photovoltaic solar power system on a portion of the former YDC property.  

Executive Summary:  In the first quarter of 2017 City Council requested information on the feasibility of installing a solar power system to Hudson’s municipal electric distribution system to help offset a portion of the City’s overall power purchases. The City’s electric system consultant Mr. John Courtney of Courtney & Associates will present information regarding the potential advantages of installing such a system, the pricing we would expect to see per KWh, and the potential offsets in power, transmission and capacity costs.    

Body

Legislative History

N/A

Purpose & Explanation

Based on the presentation material and the recommendation of the consultant staff is requesting permission to move forward with the planning of the project.

 

1.                     Further investigation and survey of proposed location and interconnection sites. 

2.                     Develop formal project costs (in-house HPP cost) for infrastructure and interconnections.

3.                     Develop RFP for project specifications timelines and construction; evaluation and recommendation of proposals

4.                     Return to Council for review of internal costs and authorization to enter into an agreement for the design and construction of the system and a power sales agreement.

Timing Considerations

 Proposed timeline:

 July-September 2017 - Develop in-house costs and RFP Document

 October - November 2017 - Advertise and select contractor

 Spring 2018 - Site work and construction

Fiscal Impact

                       Currently Budgeted

  X                       Supplemental Appropriation Required

                       Appropriation Not Required.

Recommendation

Suggested Action

Staff requests authorization to move forward with the solar project planning, advertise RFP’s for the installation of a 2 to 5 MW solar system and a power purchase agreement.

Submitted by,

Jane Howington, City Manager