Hudson logo
File #: 18-59    Version: 1 Name:
Type: Resolution Status: Passed
File created: 4/19/2018 In control: City Council
On agenda: 5/1/2018 Final action: 5/1/2018
Title: A RESOLUTION AUTHORIZING THE CITY MANAGER TO EXECUTE A CHANGE ORDER TO THE CONTRACT WITH CATTS CONSTRUCTION, INC. FOR THE VALLEY VIEW ROAD CULVERT REPLACEMENT PROJECT; AND DECLARING AN EMERGENCY. Executive Summary: Due to the need to remediate unforeseen site conditions, City staff is requesting a change to the contract with Catts Construction, Inc. for the Valley View Road Culvert Replacement Project.
Sponsors: David A. Basil
Indexes: Engineering
Attachments: 1. Resolution No. 18-59
Related files: 17-153
Title
A RESOLUTION AUTHORIZING THE CITY MANAGER TO EXECUTE A CHANGE ORDER TO THE CONTRACT WITH CATTS CONSTRUCTION, INC. FOR THE VALLEY VIEW ROAD CULVERT REPLACEMENT PROJECT; AND DECLARING AN EMERGENCY.
Executive Summary: Due to the need to remediate unforeseen site conditions, City staff is requesting a change to the contract with Catts Construction, Inc. for the Valley View Road Culvert Replacement Project.
Body
Legislative History
17-153 Permission to Advertise, Bid and Award the Valley View Culvert Replacement Project
Purpose & Explanation
The Valley View Culvert Replacement Project involves the removal and replacement of an existing 3'x5' stone/concrete box culvert that was failing due to its age (over 50 years old). Joints in the existing culvert were deteriorating, allowing for erosion and causing small voids under the road to result in settlement of the road surface. Staff determined that the best, long term repair to the issue was to remove the existing culvert and replace with a new concrete culvert which will provide a long service life (over 50 years).
Council approved a funding limit of $90,000. In order to account for potential change orders (due to unforeseen site conditions), staff is requesting an additional $9,000 - for the project bringing the revised construction contract to $99,000 ($90,000 + $9,000 = $99,000).
Timing Considerations
Upon authorization to proceed by the City Council, the administration will issue applicable Change Orders to the contract with Catts Construction Inc.
Fiscal Impact
Currently Budgeted
X Supplemental Appropriation Required (431 fund $9,000) - to be included with Quarterly Appropriations
Appropriation Not Required.

Recommendation
Suggested Action
Staff recommends that City Council approve this Resolution authorizing the City Manager to amend the contract with Catts Construction for the Valley View Culvert Replacement Project and we are requesting an emergency clause be added to this legisl...

Click here for full text