Title
Review and Discussion of a New Public Works Facility Project
Brief Description: Staff will present a review and update of the Public Works Facility Project. Mr. Jeffrey Meyers, CEO of DS Architecture will be in attendance to answer questions regarding the needs assessment and proposed project.
Body
Legislative History
File 18-0014 - Council discussion of project needs assessment and recommendation to seek professional services for design and construction management service; Council workshop of Feb. 13, 2018.
Purpose & Explanation
Staff will review the initial project needs assessment, new construction cost opinion and site location analysis. Staff will also present project options and recommendation to move the project forward.
Timing Considerations
The lease term at the Georgetown Road Facility is in the second year of a four (4) year agreement. Staff would like to begin the new project process as soon as possible.
Fiscal Impact
Currently Budgeted (Account #, $)
Supplemental Appropriation Required (Account #, $)
X Appropriation Not Required.
Recommendation
Suggested Action
Staff recommends City Council provide direction regarding moving the PW Facility Project forward, considering staff provided information and recommendations.
Submitted by,
Jane Howington, City Manager
Frank J. Comeriato, Jr., Asst. City Manager-Operations
Brad Kosco, City Engineer