I.
Preserve of Hudson Townhomes
New Residential Construction (29 Townhome Units - District 3)
Submitted by Hanna Cohan, Knez Homes, Triban Investment
a) Staff notes this case was reviewed at the May 8, 2024 and April 9, 2025
meetings.
b) The applicant has submitted revisions based on previous board
discussions. Revisions include additional variety in dormer design, porch
post design, gable end design, and front projection design.
c) Staff has compiled the attached redline revisions documenting the
observed changes; however, the applicant should present all changes to
the board.
d) Revise elevations to label exposed foundation material.
e) Question the proposed porch width and if it is functional.
f) Question if the shake siding along of lot 5 terminates at an inside corner
along the left elevation.
g) Submit the sign plan on a surveyed site plan. Staff notes the property
boundary along Darrow Road is inaccurately depicted on the submitted
sign plan.
Sponsors:
Board of Zoning & Building Appeals
Attachments:
Ms. Krickovich introduced the application by: Noting the application was reviewed on an
informal basis on May 8, 2024, describing the proposed project, and reviewing the staff
comments and recommendations.
Ms. Hanna Cohan, Triban Investments, stated her goal for this meeting is to receive feedback
from the Board in preparation for the next meeting. Ms. Cohan also distributed additional
information to the Board, and noted she is open to providing more variety to the design of the
buildings while maintaining a cohesive overall design.
The Board, applicant, and staff, discussed staff’s comments regarding the Farmhouse,
Cottage, and the Traditional style units, with Triban being open to make revisions to the
designs as suggested by staff and AHBR.
The Board noted this property which will have little or no visibility from the street.
Ms. Cohan described the proposed monument sign which will be near the road with a matt
finish, and will fit the commercial corridor where the sign will sit. The Board noted
appreciation for the proposed brick as opposed to a poured sign and that the sign will not be
near the proposed houses.
Ms. Cohan noted Triban’s desire to get full approval in April 2025 because of time limits
connected to the permits.