An update and discussion of the water plant Brine Well Project
Brief Description: Public bidding for the Brine Well Project has been completed. The Project ROI calculations have been attached for review. Staff wishes to review the bid status and discuss the project options moving forward with City Council.
Body
Legislative History
Res. No. 16-195 - Authorization for the City Manager to enter into a contract for design and project management services for the water plant brine well project.
Purpose & Explanation
The Water Plant Brine Well Project advertised for public bid on 9-23-18. Three bids were received with the lowest bid being $1,507,822.00, or $307,822 (26%) over the engineer’s estimate of $1,200,000. After rejecting the bids due to the cost being 10% over the estimate, staff spoke with the general contractors who supplied bids and identified that only one drilling sub-contractor was available to perform the work in the time allotted for the project which may have caused the bids to come in higher than anticipated.
Prior to rebidding the project, in an effort to lower project costs, City staff and the design consultant for the project refined the project schedule and contacted additional general contractors, drilling companies, the Ohio Department of Natural Resources (ODNR) to attract a larger pool of bidders. The project was rebid, and opened on 12-21-18, still with three bidders. The results of the rebid are:
Bid Amounts (Rebid):
1. Nerone & Sons, Inc.--------------------$1,549,050
2. Workman Industrial Services-------$1,575,793
3. Lockhart Concrete Co.-----------------$1,697,880
The revised project construction budget is:
Low Bid…………………………………………………$1,549,050
Project Contingency (10%)…………………………$154,905
Total Construction Cost………………………….$1,703,955
Original Construction Estimate…………………….$1,200,000
Construction Cost Overage …………………………$503,955
Fiscal Impact
X Currently Budgeted
X Supplemental Appropriation Required
Appropriation Not Required.
Recommendation
Suggested Action
City staff is seeking input and direction from City Council on the project prior to awarding the bid.
Submitted by,
Jane Howington, City Manager
Frank Comeriato, Jr. Asst. City Manager - Operations
Brad Kosco, City Engineer
Kevin Powell, Asst. Public Works Director-Utilities