Title: A MOTION TO REJECT BIDS FOR THE SUM-91-15.20 N. MAIN STREET AND PROSPECT STREET INTERSECTION IMPROVEMENTS (PID 88548) WHICH EXCEEDED THE ENGINEER'S ESTIMATE BY 10% AND TO AUTHORIZE THE RE-BIDDING OF THE WORK; AND DECLARING AN EMERGENCY. Executive Summary: The project includes the signal, roadway, pedestrian walks, and improvements to the pavement and pedestrian access at the Prospect and SR 91 intersection.
Sponsors: William A. Currin
Indexes: Engineering
Related files: 15-28, 15-1, 14-88, 12-114, 16-187
Title
A MOTION TO REJECT BIDS FOR THE SUM-91-15.20 N. MAIN STREET AND PROSPECT STREET INTERSECTION IMPROVEMENTS (PID 88548) WHICH EXCEEDED THE ENGINEER'S ESTIMATE BY 10% AND TO AUTHORIZE THE RE-BIDDING OF THE WORK; AND DECLARING AN EMERGENCY.
Executive Summary: The project includes the signal, roadway, pedestrian walks, and improvements to the pavement and pedestrian access at the Prospect and SR 91 intersection.
Body
Legislative History
Resolution 12-29 ODOT/LPA Agreement.
Resolution 12-114 Arcadis Design fee approved, authorized contract for engineering design
Resolution 14-88 Arcadis Modification approved for plan revisions due concept change
Resolution 15-1 Purchase of Real Property with Diocese of Cleveland
Resolution 15-28 Authorizing City Manager to Advertise for Bids
Purpose & Explanation
Bids were received on July 28, 2015 for the SUM-91-15.20 N. Main Street and Prospect Street Intersection Improvements. Below is the Engineer's Estimate along with the respective bids.
Engineer's Estimate: $902,088.62
Ronyak Paving, Inc. $1,235,976.97

Due to the bid exceeding the Engineer's Estimate in excess of 10% (37% above engineer's estimate) we are recommending rejection of the bid. Engineering will rebid the project closer to 2016 for 2016 completion, adjusting the plans and estimate as needed, based on contractor feedback.
Timing Considerations
This project will be rebid at the end of 2015 for 2016 construction.
Fiscal Impact
X Currently Budgeted ($170,000 - 2015 Budget (City's 20%), $761,760 (Fed. Funds))
Supplemental Appropriation Required
Appropriation Not Required.

Recommendation
Suggested Action
Staff recommends rebidding the project for 2016 work. Staff will be adjusting plans, project notes, and the estimate as needed. Staff also recommends that City Council approve a motion to reject the Ronyak Paving, Inc. bid and authorize the re-bidding of this project.
Submitted by,
Jane Howington, City Manager