File #: 18-32    Version: 1 Name:
Type: Resolution Status: Passed
File created: 2/21/2018 In control: City Council
On agenda: 3/6/2018 Final action: 3/6/2018
Title: A RESOLUTION AUTHORIZING THE CITY MANAGER TO SUBMIT AN APPLICATION TO THE NORTHEAST OHIO REGIONAL SEWER DISTRICT FOR FUNDING ASSISTANCE THROUGH THE NEORSD COMMUNITY COST SHARE PROGRAM, TO ADVERTISE FOR BIDS AND TO ENTER INTO A CONTRACT FOR THE 2018 STORM SEWER LINING IMPROVEMENTS WITH THE LOWEST AND BEST BIDDER; AND DECLARING AN EMERGENCY. Executive Summary: This project involves the lining of storm sewers throughout the City and application to the Northeast Ohio Regional Sewer District (NEORSD) for funding reimbursement via the NEORSD Community Cost Share Program.
Sponsors: David A. Basil
Indexes: Engineering, Finance - Appropriations and Budget, Public Works - Services
Attachments: 1. Master Storm Lining List, 2. Resolution No. 18-32
Title
A RESOLUTION AUTHORIZING THE CITY MANAGER TO SUBMIT AN APPLICATION TO THE NORTHEAST OHIO REGIONAL SEWER DISTRICT FOR FUNDING ASSISTANCE THROUGH THE NEORSD COMMUNITY COST SHARE PROGRAM, TO ADVERTISE FOR BIDS AND TO ENTER INTO A CONTRACT FOR THE 2018 STORM SEWER LINING IMPROVEMENTS WITH THE LOWEST AND BEST BIDDER; AND DECLARING AN EMERGENCY.
Executive Summary: This project involves the lining of storm sewers throughout the City and application to the Northeast Ohio Regional Sewer District (NEORSD) for funding reimbursement via the NEORSD Community Cost Share Program.
Body
Legislative History
None.
Purpose & Explanation
Staff has identified that the primary source of storm sewer related work orders continues to be due to sink holes caused by failing joints within storm pipes. Public Works staff repairs a number of individual failing pipe joints each year and has utilized a storm sewer lining program since 2006 to repair several sewers with separated joints throughout the City.
Compared to the traditional method of excavating and spot repairing individual storm sewer joints, storm sewer lining is much less intrusive than traditional excavation, causes fewer disruptions to the public and extends the life of the entire length of the storm sewers by approximately 50 years.
The City's 2018 budget has allocated $75,000 for storm sewer lining. Staff is requesting a supplemental appropriation of $75,000, to be reimbursed by the NEORSD Community Cost Share Program, to line two additional, large diameter storm sewers in 2018.
City staff maintains a dynamic list of the worst storm sewers for which lining is recommended. The list changes as more of the storm sewer system is televised and other problem areas are identified. Staff will continue to develop and maintain the capital budget plan to allocate the necessary City funds to eliminate sink holes as the top source of work orders regarding storm sewer maintenance.
Timing Considerations
Following the app...