Hudson logo
File #: 18-44    Version: 1 Name:
Type: Resolution Status: Passed
File created: 3/13/2018 In control: City Council
On agenda: 3/20/2018 Final action: 3/20/2018
Title: A RESOLUTION AUTHORIZING THE CITY MANAGER TO ENTER INTO AN ADDENDUM TO A PROFESSIONAL SERVICES CONTRACT WITH ENVIRONMENTAL DESIGN GROUP FOR ADDITIONAL PROFESSIONAL ARCHITECTURAL CONSULTING SERVICES RELATING TO THE CONSTRUCTION OF THE SCHOOL DISTRICT BUS GARAGE AND CITY SALT STORAGE FACILITY PROJECT; AND DECLARING AN EMERGENCY. Executive Summary: This Resolution would authorize a $40,000 increase to the original design contract for the architectural consulting services relating to the construction of the new School Bus Garage and Salt Storage Facility Project.
Sponsors: David A. Basil
Indexes: Engineering, Finance - Appropriations and Budget
Attachments: 1. Resolution No. 18-44
Related files: 16-134
Title
A RESOLUTION AUTHORIZING THE CITY MANAGER TO ENTER INTO AN ADDENDUM TO A PROFESSIONAL SERVICES CONTRACT WITH ENVIRONMENTAL DESIGN GROUP FOR ADDITIONAL PROFESSIONAL ARCHITECTURAL CONSULTING SERVICES RELATING TO THE CONSTRUCTION OF THE SCHOOL DISTRICT BUS GARAGE AND CITY SALT STORAGE FACILITY PROJECT; AND DECLARING AN EMERGENCY.
Executive Summary: This Resolution would authorize a $40,000 increase to the original design contract for the architectural consulting services relating to the construction of the new School Bus Garage and Salt Storage Facility Project.
Body
Legislative History
Res. No. 16-134 - Permission to enter into an agreement with Environmental Design Group (EDG Group) for the final design and associated professional architectural services for the construction of the City's new salt dome and bus garage on City-owned property located at 5810 Hudson Drive (former Koberna site).
Purpose & Explanation
The additional work to the Environmental Design Group Contract is $40,000 over the original contract amount of $424,953 for the required architectural inspection and observation services needed over the original contract.

The change to the contract includes the additional architectural inspection and observation services for the project by the design engineer and architect. The City team has reviewed the construction contracts, has met with the project building contractor, and has met with several public officials with building inspection construction experience on this type of work. The City team has determined this course would be in the best interest of the City of Hudson and Hudson School District for this project. The City administration was able to reallocate existing City Engineering inspection staff to perform the site inspection and construction administration services for the Bus Garage and Salt Storage Project and not rely on a private construction management firm for this project.

Anthony Calabro (Hudson Construction Inspector) ...

Click here for full text