A RESOLUTION AUTHORIZING THE CITY MANAGER TO ADVERTISE FOR BIDS AND TO ENTER INTO A CONTRACT FOR CONSTRUCTION OF A NEW HUDSON CITY SCHOOLS BUS GARAGE FACILITY AND CITY SALT STORAGE STRUCTURE WITH THE LOWEST AND BEST BIDDER; AND DECLARING AN EMERGENCY.
Executive Summary: As part of the preparations for the Downtown Phase II project the former Hudson Public Power Facilities, Hudson City Schools Bus Garage and the City's salt storage will need to be relocated. The new City salt storage structure and Hudson City Schools bus garage will be constructed at 5778 Hudson Drive (former Koberna Property).
Body
Legislative History
Res. No. 15-117 - Enter into a contract with EDG for professional services for the relocation of the bus garage and salt storage structure, passed 8/18/15.
Res. No. 15-166 - Accepted grant funding from the Summit County Land Reutilization Corporation for re-use of the site of the current bus garage, HPP and salt dome, passed 10/20/15.
Res. No. 15-195 - Enter into a contract with EDG for Phase II for environmental studies, passed 12/15/15.
Res. No. 16-79 - Authorization to solicit RFP's for the final design and professional services for the relocation of the bus garage and salt storage structure, passed 5/17/16.
Res. No. 16-134 - Authorization to enter into a contract for final design and professional services for the relocation of the bus garage and salt storage structure, passed 8/16/16.
Res. No. 17-74 - Accepted grant funding from the Summit County Land Reutilization Corporation for re-use of the former Koberna Property for the development of the bus garage and salt storage structure, 5/2/17.
Purpose & Explanation
The proposed work consists of a salt storage facility and a school bus garage facility.
Salt Storage Facility
The salt storage facility is composed of a 9,800 square foot building storing approximately 4,000 tons of salt, 10,000 gallons of brine storage and includes a small single person restroom and storage room. The facility...