File #: 16-4    Version: 1 Name:
Type: Resolution Status: Passed
File created: 12/22/2015 In control: City Council
On agenda: 1/19/2016 Final action: 1/19/2016
Title: A RESOLUTION AUTHORIZING AND DIRECTING THE CITY MANAGER TO ADVERTISE FOR BIDS FOR THE NORTH MAIN STREET - DOWNTOWN CORRIDOR IMPROVEMENTS SUM-91-14.67 PROJECT (ODOT PID 93820) AND THE PROCUREMENT OF SIGNAL POLES IN THE CITY OF HUDSON, OHIO; AND DECLARING AN EMERGENCY. Executive Summary: This project consists of the reconstruction of the N. Main Street (SR 91) from Streetsboro Street (SR 303) to Owen Brown Street. The project also includes the replacement of the waterline, pervious pavers, stamped colored concrete walks, lighting, retaining wall, a new traffic signal at N. Main Street and Clinton/Aurora Streets, street trees, storm sewer work and other streetscape improvements.
Sponsors: David A. Basil
Indexes: Engineering
Attachments: 1. Resolution No. 16-4
Related files: 14-113, 13-161, 12-134, 13-151, 14-101, 16-63, 16-0030
Title
A RESOLUTION AUTHORIZING AND DIRECTING THE CITY MANAGER TO ADVERTISE FOR BIDS FOR THE NORTH MAIN STREET - DOWNTOWN CORRIDOR IMPROVEMENTS SUM-91-14.67 PROJECT (ODOT PID 93820) AND THE PROCUREMENT OF SIGNAL POLES IN THE CITY OF HUDSON, OHIO; AND DECLARING AN EMERGENCY.
Executive Summary: This project consists of the reconstruction of the N. Main Street (SR 91) from Streetsboro Street (SR 303) to Owen Brown Street. The project also includes the replacement of the waterline, pervious pavers, stamped colored concrete walks, lighting, retaining wall, a new traffic signal at N. Main Street and Clinton/Aurora Streets, street trees, storm sewer work and other streetscape improvements.
Body
Legislative History
11-111: Applied to AMATS for Federal Funding
12-134: Entered into a LPA Agreement with ODOT for N. Main St. Downtown Corridor Improvements SUM-91-14.67 (PID 93820)
13-151: Applied to AMATS for additional Federal Funding
13-161: Entered into contract with GPD Group for design services
14-101: Entered into an Agreement with Ohio EPA for Grant
14-113: Entered into an amended LPA Agreement with ODOT for additional funding
Purpose & Explanation
The current project includes: replacing the signal at Main Street (SR 91) and Clinton and Aurora Streets; full depth pavement replacement on Main Street (SR 91) from Streetsboro Street (SR 303) to Owen Brown Street including pavement replacement of side street pavement to tie in the new profile; replacing curbs and resetting some sandstone curbs; replacing waterline (circa 1912); replacing and adding portions of storm sewer. Installation of actuated cross walk signals at: mid-block between Church Street and Aurora Streets; replacing walks with stamped and dyed concrete walks from Streetsboro Street (SR 303) to Owen Brown Street, with pervious pavers, street trees, benches, landscaping and other miscellaneous hardscape items, pedestrian and Cobra lighting with LED lights; creating a new walk on the east...

Click here for full text