Title: A RESOLUTION AUTHORIZING THE CITY MANAGER TO ENTER INTO A CONTRACT WITH PERRIN ASPHALT COMPANY, INC. FOR THE ELLSWORTH HILL SAFE ROUTES TO SCHOOL PROGRAM (PID 96866); AND DECLARING AN EMERGENCY. Executive Summary: The project will include the installation of a concrete sidewalk on Parkside Drive from the intersection of Stow Road to Blue Heron Drive
Sponsors: William A. Currin
Indexes: Engineering
Attachments: 1. Ellsworth Hill SRTS - Bid Tabulation, 2. Resolution No. 15-54
Related files: 13-18, 14-144, 15-29, 15-112
Title
A RESOLUTION AUTHORIZING THE CITY MANAGER TO ENTER INTO A CONTRACT WITH PERRIN ASPHALT COMPANY, INC. FOR THE ELLSWORTH HILL SAFE ROUTES TO SCHOOL PROGRAM (PID 96866); AND DECLARING AN EMERGENCY.
Executive Summary: The project will include the installation of a concrete sidewalk on Parkside Drive from the intersection of Stow Road to Blue Heron Drive
Body
Legislative History
Resolution #10-121-Authorization to develop the school travel plan
Resolution #12-20-Authorization to Apply to SRTS (2012)
Resolution #13-18-Authorization to Apply to SRTS (2013)
Resolution #14-144-Enter into LPA Agreement
Resolution #15-29-Authorization to Advertise for Bids

Purpose & Explanation
Bids were received on Friday, April 3, 2015 for the Ellsworth Hill Safe Routes to School Program (PID 96866). Below is the Engineer's Estimate along with the respective bids.
Engineer's Estimate: $127,478.20
Perrin Asphalt Company, Inc. $106,757.26
Daniel A. Terreri & Sons, Inc. $109,748.40
Spano Brothers Construction Co., Inc. $135,856.86
Perk Company, Inc. $216,340.60

The City Administration is requesting City Council approval to authorize the City Manager to award and enter into a contract with Perrin Asphalt Company, Inc. for the Ellsworth Hill Safe Routes to School Program (PID 96866). The Engineering Staff is requesting a 10% contingency for any unforeseen issues that may arise during construction. The total amount would be $117,432.99.
Total Contract = $117,432.99 ($106,757.26-base + $10,675.73-contingency)
The City of Hudson received a grant from ODOT for SRTS for $50,000.00.
Timing Considerations
Upon authorization to proceed by the City Council, the administration will award and enter into a contract with Perrin Asphalt Company, Inc. for the above amounts.
Fiscal Impact
X Currently Budgeted ($75,000 - 430 fund)
Supplemental Appropriation Required
Appropriation Not Required.

Recommendation
Suggested Action
Staff recommends that City...

Click here for full text