File #: 18-58    Version: 1 Name:
Type: Resolution Status: Passed
File created: 4/20/2018 In control: City Council
On agenda: 5/1/2018 Final action: 5/1/2018
Title: A RESOLUTION AUTHORIZING THE CITY MANAGER TO ENTER INTO A PROFESSIONAL SERVICES CONTRACT WITH O.R. COLAN ASSOCIATES, INC. FOR RIGHT-OF-WAY ACQUISITION SERVICES FOR THE STATE ROUTE 91 NORTH TURN LANE IMPROVEMENTS PROJECT (PID 93822); AND DECLARING AN EMERGENCY. Executive Summary: The SR 91 North Turn Lane Improvement project design includes the addition of left turn lanes at Valley View Road, Herrick Park Drive & Hines Hill Road, resurfacing of SR 91 from Brandywine Drive to Middleton Road, the installation of a sidewalk on one east side of the road, and bike lanes on both sides of the road from Brandywine Drive to Middleton Road.
Sponsors: David A. Basil
Indexes: Engineering, Finance - Appropriations and Budget
Attachments: 1. Review Cost Breakdown, 2. Resolution No. 18-58
Related files: 14-113, 15-13, 16-67, 17-7, 20-49, 19-44, 19-69, 19-60, 19-114, 20-3, 19-43, 19-77, 19-68, 18-57, TMP-3993, TMP-3995, TMP-3996, TMP-3997, TMP-3998, TMP-3999, 19-37, 19-36, 19-59, 19-67, 19-78, TMP-4033, TMP-4034, TMP-4035, TMP-4036, 19-94, 19-99, 19-100, 19-101, 19-120, 19-144, 19-176, 20-12, 20-63
Title
A RESOLUTION AUTHORIZING THE CITY MANAGER TO ENTER INTO A PROFESSIONAL SERVICES CONTRACT WITH O.R. COLAN ASSOCIATES, INC. FOR RIGHT-OF-WAY ACQUISITION SERVICES FOR THE STATE ROUTE 91 NORTH TURN LANE IMPROVEMENTS PROJECT (PID 93822); AND DECLARING AN EMERGENCY.
Executive Summary: The SR 91 North Turn Lane Improvement project design includes the addition of left turn lanes at Valley View Road, Herrick Park Drive & Hines Hill Road, resurfacing of SR 91 from Brandywine Drive to Middleton Road, the installation of a sidewalk on one east side of the road, and bike lanes on both sides of the road from Brandywine Drive to Middleton Road.
Body
Legislative History
17-7: Authorization to Enter into Contract with ms Consultants for the Final Design Phase of Engineering Design
16-67: Discussion: The SR 91 North Turn Lane Improvements, Costs Estimates and Recommendations
15-13: Authorization to Enter into Contract with ms Consultants for the First Phase of Engineering Design
14-113: Authorization to Amend LPA Agreement and Funding Commitment with ODOT
12-35: Authorization for City to enter into Lead Public Agency (LPA) with ODOT
11-111: Authorization to Apply for STP funds as Programmed by AMATS
Purpose & Explanation
The study and design of the State Route 91 North Turn Lane Improvements is nearing completion. The project design includes improvements to the roadway shoulder, storm sewer and lighting improvements, a new 8-foot pedestrian sidewalk on the east side of the road, two 12-foot through lanes, new 11-foot turn lanes at the Valley View Road, Herrick Park Drive and Hines Hill Road intersections, 5-foot bike lanes on both sides of the road and a drainage/water quality swale on the west side of the road and resurfacing of the entire project corridor. The project is expected to be bid in 2019 with construction scheduled for 2019-2020.
Due to the widening of the roadway and other improvements, temporary and permanent right-of-way acquisitions are required ...